- Issue
-
Aids & adaptations service delays
- Source
-
RSH / HQN
- Root cause
-
Reactive delivery model; no formal policy or business case
- Specific activities
-
- Develop and approve A&A policy and business case
- Re-negotiate contractor SLA for target turnaround times
- Measurable outcomes
-
- ≥ 90 % of adaptations completed within 10 weeks of request
- Achievable resources and inputs
-
- Policy working group (Housing, Finance, Procurement)
- External consultant input
- Relevant consumer standard
-
Consumer Standard: Neighbourhood & Community
- Milestones
-
- Policy to be approved by Cabinet in November
- Continuation to report quarterly figures in PAF
- Review of budgetary spend 2023/24 and 2024/25 this will be fed into correct budge
- Target Date
-
31-Dec-25
- Responsible / accountable
-
Lead: Asset Manager
Accountable: Head of Housing
- Status
-
In progress
- Monitoring and evidence
-
- Policy document version control in Teams
- SLA sign-off scanned to Monday.com; monthly delivery report