Record details

Issue
Aids & adaptations service delays
Source
RSH / HQN
Root cause
Reactive delivery model; no formal policy or business case
Specific activities
  • Develop and approve A&A policy and business case
  • Re-negotiate contractor SLA for target turnaround times
Measurable outcomes
  • ≥ 90 % of adaptations completed within 10 weeks of request
Achievable resources and inputs
  • Policy working group (Housing, Finance, Procurement)
  • External consultant input
Relevant consumer standard
Consumer Standard: Neighbourhood & Community
Milestones
  • Policy to be approved by Cabinet in November
  • Continuation to report quarterly figures in PAF
  • Review of budgetary spend 2023/24 and 2024/25 this will be fed into correct budge
Target Date
31-Dec-25
Responsible / accountable
Lead: Asset Manager
Accountable: Head of Housing
Status
In progress
Monitoring and evidence
  • Policy document version control in Teams
  • SLA sign-off scanned to Monday.com; monthly delivery report