Record details

Issue
Repairs backlog & performance
Source
RSH / HQN
Root cause
Poor data quality, no systematic timetable for outstanding jobs
Specific activities
  • Cleanse live repairs data; validate backlog
  • Implement weekly “backlog blitz” action plan
Measurable outcomes
  • Outstanding jobs >30 days down to < 5 % of total
  • Emergency repair target met in 95 % of cases
Achievable resources and inputs
  • Contractor liaison meetings
  • Use ActiveH scheduling module
Relevant consumer standard
Consumer Standard: Repairs & Maintenance
Milestones
  • Reduction in overall numbers due to weekly contractor liaison meetings
Target Date
31-Mar-26
Responsible / accountable
Lead: Compliance Manager

Accountable: Head of Assets
Status
In progress
Monitoring and evidence
  • Weekly KPI dashboard
  • Evidence folder with before/after backlog reports; contractor meeting minutes