- Issue
-
Repairs backlog & performance
- Source
-
RSH / HQN
- Root cause
-
Poor data quality, no systematic timetable for outstanding jobs
- Specific activities
-
- Cleanse live repairs data; validate backlog
- Implement weekly “backlog blitz” action plan
- Measurable outcomes
-
- Outstanding jobs >30 days down to < 5 % of total
- Emergency repair target met in 95 % of cases
- Achievable resources and inputs
-
- Contractor liaison meetings
- Use ActiveH scheduling module
- Relevant consumer standard
-
Consumer Standard: Repairs & Maintenance
- Milestones
-
- Reduction in overall numbers due to weekly contractor liaison meetings
- Target Date
-
31-Mar-26
- Responsible / accountable
-
Lead: Compliance Manager
Accountable: Head of Assets
- Status
-
In progress
- Monitoring and evidence
-
- Weekly KPI dashboard
- Evidence folder with before/after backlog reports; contractor meeting minutes