Schedule for building improvements

New leisure operator took over on 1st June

Everyone Active took over the management of leisure centres from 1st June 2017. For information about the centres, including prices and bookings, please visit www.everyoneactive.com.

Newbold Comyn Leisure Centre

Building works commenced at Newbold Comyn Leisure Centre on 3rd January 2017 and required a complete closure of this centre. The swimming pool, brand new 100 station gym and fitness studios reopened on Monday 21 August 2017, with temporary reception and additional overflow changing provision, until the completion of the village changing facilities and sports hall in Spring 2018.

St Nicholas Park Leisure Centre

St Nicholas Park Leisure Centre swimming pool closed on 11th December 2016. The swimming pool and new changing rooms reopened 6 weeks ahead of schedule on Thursday 21st September 2017.

In early June the existing gym at St Nicholas Park was refurbished and new equipment installed enhancing the gym offering for our customers until the new 80 station gym opens in Spring 2018.

Leisure centre customer leaflet - phase one open dates and information

A flavour of how the centres will look

Gym interior
(this is another Everyone Active gym)
New gym interior
Gym interior
(this is another Everyone Active gym)
New gym interior and treadmills
Gym interior
(this is another Everyone Active gym)
New gym interior
St Nicholas Park - front St Nicholas Park visual of new building
St Nicholas Park - interior St Nicholas Park leisure centre interior
Newbold Comyn - front Newbold Comyn Leisure Centre - visual of new building
Proposals for climbing
facilities at Newbold
Conceptual drawing of climbing facilities

Photos of the work in progress

Work in progress

Sign up for email updates

Sign up to receive updates about the improvement work

Timeline

Work is continuing to confirm the actual dates for the works, but broadly we anticipate the following outline timeframe

Date Progress
December 2016 Work commenced at St Nicholas Park Leisure Centre
January 2017 Works commenced at Newbold Comyn Leisure Centre
June 2017 The existing gym at St Nicholas Park was refurbished and new equipment installed
August 2017 The swimming pool, brand new 100 station gym and fitness studios will reopen at Newbold with additional overflow changing provision
September 2017 The swimming pool and new changing rooms will reopen at St Nicholas Park
Spring 2018 Works completed at both sites and both fully open